Redrow Homes – Heritage Fields, Nuneaton Multi Utilities

redrow, heritage, fields, nuneaton, multi, utilities

Heritage Fields was our first appointment as Multi Utilities provider for Redrow Homes. The project started in October 2019 and comprised of gas, water and electricity mains/services for a collection of 200 new homes.

During the course of our off-site gas works, the gas main we were supposed to connect to was found to be smaller than mapped. The alternative connection point offered, meant crossing a busy A road which lead to a challenging consultation with Highways England. We were able to organise this and the necessary licences without any delays to the build programme.

Works are ongoing and will be completed early 2022.